Queue item twelve, and the tenth article this session. Item eleven was re-gated and declined, because a clear score on vocabulary is not the same as a genuinely different subject and the map's own note said so. This one gates clean and produces the starkest single number we have computed in this programme.

Key Takeaway

The aggregate licence fee is distributed roughly 61 percent to the local municipality, 15 percent to the upper tier, and 3 percent to the Aggregate Resources Trust for rehabilitation AND research. Municipalities receive about twenty-five dollars for every one that goes to rehabilitation and research combined. The fee is a municipal revenue instrument that carries a rehabilitation programme as a rider.

The Verdict, Stated First

Five claims, in descending order of confidence.

One. Aggregate licence fees are distributed overwhelmingly to municipalities. On the trustee's own published statement, fees collected from licences, wayside permits and aggregate permits are distributed approximately 61 percent to the local municipality, 15 percent to the upper-tier municipality, and 3 percent to the Aggregate Resources Trust for rehabilitation and research [1].

Two. On our own arithmetic that is a ratio of 25.3 to one. Municipalities take 76 percent of the fee. Rehabilitation and research together take three.

Three. The abandoned site programme runs on roughly $400,000 to $600,000 a year. That figure comes from the programme's own co-ordinator, described as based on recent levels of extraction in the province [4].

Four. Against a legacy backlog put at approximately 7,900 sites or more, that is $50.63 to $75.95 per site per year. Ours, and it is division.

Five. At a rehabilitation cost of $150,000 a site, clearing the backlog takes between 1,975 and 2,962 years, assuming no new abandonments and no cost inflation. Least confident of the five, because the $150,000 is our assumption and we could not source a per-site cost. At $50,000 it is 658 to 988 years. At $250,000 it is 3,292 to 4,938. Every figure in that range is a number nobody could describe as a programme with an end.

Our Grades For These Claims

We grade our own sourcing before anyone else has to.

Claim one is from the trustee itself. The Ontario Aggregate Resources Corporation publishes the fee distribution on its own site, and it appears identically across its 2023-24, 2024-25 and 2025-26 fee notices. Three consecutive years stating the same split is about as stable as a secondary fact gets.

Claims two, four and five are arithmetic on the figures in one and three. They depend on no source beyond those and can be checked in a minute.

Claim three is a quoted statement from a programme co-ordinator, reproduced in two independent secondary sources. It is a person describing their own programme's budget, which is good evidence, and it is not an audited figure and we did not obtain the Trust's financial statements.

The 7,900 site figure is the weakest number in the article and it carries claims four and five. It comes from testimony at 2012 hearings on the Aggregate Resources Act, reproduced in a public interest group's paper. It is fourteen years old at the date we write, it was an advocacy submission, and the speaker's own phrasing was approximately 7,900 sites or more. We flag it every time we use it.

The per-tonne fee rates are historical. The 11.5 cent figure and its component breakdown come from older provincial and secondary material. The trustee states that fees are adjusted annually for inflation under Regulation 244/97 following the Ontario Consumer Price Index, so the current cents-per-tonne figure is higher and we did not obtain it. We use the percentage distribution, which the trustee publishes currently, and treat the cents figures as historical illustration.

A Note On Method

What we obtained: the Ontario Aggregate Resources Corporation's published fee notices for 2023-24, 2024-25 and 2025-26, used for the current percentage distribution and for the annual CPI adjustment mechanism; Ontario's aggregate resources pages, used for the description of the Management of Abandoned Aggregate Properties programme and the compliance assessment report obligation; a provincial policy document, used for the historical 11.5 cent fee and its component breakdown; a reproduction of O. Reg. 244/97, used for the annual production report and annual fee provisions and the minimum royalty; and two public interest papers, used for the programme co-ordinator's statement of annual funding, for the origin of the half-cent dedication in 1990, and for the 7,900 site figure.

What we did NOT obtain:

  • The Aggregate Resources Act itself. Everything statutory here reaches us through regulation text, provincial policy documents or the trustee's description.
  • The current cents-per-tonne fee. The trustee states fees are adjusted annually and posted before 1 January. We did not retrieve the current figure.
  • The Aggregate Resources Trust's financial statements. The $400,000 to $600,000 is a quoted statement, not an audited number.
  • Any current count of abandoned sites. Our figure is from 2012 testimony.
  • Any per-site rehabilitation cost. The $150,000 we use is invented and we show the sensitivity across a wide band because of it.
  • The site plan and security requirements for licensed operators. We describe the separation between the fee-funded legacy programme and an operator's own rehabilitation obligation without having read the provisions governing the latter.

One framing note. This article is about the legacy programme and the fee that funds it. A licensed operator's obligation to rehabilitate its own site is a different mechanism, and we treat that separation as the article's second finding rather than blurring the two.

Two Rehabilitation Problems, Not One

Before any arithmetic, a distinction that a great deal of commentary on this sector runs together.

Ontario has two aggregate rehabilitation problems and they are funded in completely different ways.

The first is the licensed operator's own site. A pit or quarry operating under a licence has a site plan, obligations to rehabilitate progressively as extraction advances and finally when it ends, and reporting obligations including an annual compliance assessment report submitted to the ministry and, where the site is in a municipality, to that municipality as well.

The second is the legacy site. Pits and quarries on private land that stopped operating before they were required to obtain a licence. Ontario's own description is that where the landowner has granted permission, these sites can be rehabilitated by the Ontario Aggregate Resources Corporation under the Management of Abandoned Aggregate Properties programme [3].

These are different in every respect that matters. The first has an identifiable obligor with a licence to lose. The second has no obligor at all, which is precisely what makes it a legacy problem: the extraction happened before the regime existed.

The fee this article is about funds the second, not the first. An operator paying its per-tonne fee is not pre-funding the rehabilitation of its own pit. It is contributing to a programme that fixes somebody else's, abandoned decades before the operator existed.

That is a defensible piece of policy design and it is worth stating plainly, because an operator that believes its fees are building a fund for its own site has misunderstood what it is paying for.

Where The Fee Actually Goes

The trustee publishes the distribution, and it is the same in each of the three most recent fee notices we read: fees collected from licences, wayside permits and aggregate permits are distributed approximately 3 percent to the Aggregate Resources Trust for rehabilitation and research, 61 percent to the local municipality in which the site is located, and 15 percent to the upper-tier municipality.

The remainder, which on those figures is around 21 percent, goes to the Crown.

Ours, restating that as a hierarchy:

  • Local municipality: 61 percent
  • Crown and remainder: 21 percent
  • Upper-tier municipality: 15 percent
  • Rehabilitation and research: 3 percent

Municipalities together take 76 percent. Rehabilitation and research together take three. The ratio is 25.3 to one.

And note the conjunction in that last line. The three percent is not a rehabilitation allocation. It is a rehabilitation and research allocation, and the trustee's stated responsibilities include the collection and publication of production statistics and other information, and the education and training of those in or interested in the aggregate industry. Those are worthwhile activities funded from the same three percent.

So the share of the aggregate fee that reaches rehabilitation is something below three percent, and we cannot tell you how far below because we did not obtain the Trust's accounts.

What That Makes The Fee

Ours, and stated as a characterisation rather than a criticism.

A levy that sends 76 percent of its proceeds to the municipalities hosting the activity, 21 percent to the Crown, and 3 percent to remediation and research is not primarily an environmental instrument. It is a municipal revenue-sharing instrument that carries a rehabilitation programme as a rider.

There is a perfectly good rationale for the municipal share. A host municipality bears the road wear, the truck traffic, the dust, the noise and the planning burden of an extraction operation, and receives no property tax uplift proportionate to the tonnage moving through it. A per-tonne payment to the host is compensation for externalities borne locally, and 61 percent to the lower tier plus 15 to the upper is a reasonable way to allocate that.

None of which changes what the remaining three percent has to do.

We make the point because of how this fee is usually described. The presence of an abandoned pits fund inside the levy invites the reading that extraction pays for its own cleanup. On the published distribution it does not, in either sense: the fee does not fund the payer's own site, and the slice that funds anyone's site is three percent of a levy that is mostly doing something else.

The honest description is that Ontario funds legacy aggregate rehabilitation from a minority rider on a municipal compensation levy, and the size of that rider was set by agreement in 1990.

A Number Chosen In 1990

The origin of the dedication is worth recording because it explains the size.

On the account given by the programme's co-ordinator and reproduced in two public interest papers, when the Aggregate Resources Act came into effect in 1990 the aggregate industry, through the association now known as the Ontario Stone, Sand and Gravel Association, decided to dedicate half a cent per tonne of the licence fees paid by producers to a programme responsible for rehabilitating legacy sites [4].

Read what that sentence describes. The industry decided. The amount was arrived at by agreement among the parties who would pay it, at the outset of a regulatory regime, and it was expressed as a fixed number of cents rather than as a proportion of the problem.

Against the historical 11.5 cent fee [2], half a cent is 4.35 percent of the fee. The current percentage distribution puts the Trust's share at three percent, which is in the same territory once research is inside the same allocation.

Ours, and offered as the structural observation. A dedication expressed in cents per tonne is indexed to extraction volume. It is not indexed to the number of abandoned sites, to the cost of rehabilitating one, or to the rate at which the backlog is being cleared. Those are the three quantities that determine whether the programme finishes, and the funding formula is connected to none of them.

Fees are adjusted annually for inflation under Regulation 244/97 following the Ontario Consumer Price Index, so the real value of the dedication holds. What it does not do is respond to the size of the task.

Fifty Dollars A Site

Now the division, and it is only division.

The programme co-ordinator's stated figure is that based on recent levels of extraction in the province, approximately $400,000 to $600,000 is made available annually for the programme.

The backlog figure comes from testimony at 2012 hearings on the Act, where it was put that thousands of pits and quarries in Ontario, either abandoned at approximately 7,900 sites or more or under licence or permit, had not undergone progressive or final rehabilitation. This is the weakest number in the article, it is fourteen years old, and it came from an advocacy submission.

Ours, dividing one by the other:

  • At $400,000 a year across 7,900 sites: $50.63 per site per year
  • At $500,000: $63.29
  • At $600,000: $75.95

Fifty to seventy-six dollars, per abandoned pit, per year.

That is not a rehabilitation budget. It is roughly the cost of one site visit per site per decade, and the programme is not attempting to spread the money that way, because it cannot. It rehabilitates a small number of sites properly and does nothing at all at the rest, which is the correct response to a budget of that size and is also the reason the per-site figure is the honest way to express it.

And How Long That Takes

Express the same numbers as a completion horizon and the picture is starker.

We could not source a per-site rehabilitation cost, so we show the sensitivity across a wide band. Ours, assuming no new abandonments and no cost inflation, both of which are generous assumptions:

  • At $50,000 a site: 658 to 988 years
  • At $100,000: 1,317 to 1,975 years
  • At $150,000: 1,975 to 2,962 years
  • At $250,000: 3,292 to 4,938 years
  • At $500,000: 6,583 to 9,875 years

There is no assumption in that band that produces a horizon within any meaningful planning period. The cheapest cost against the most generous funding still runs 658 years.

We want to be careful about what this does and does not show. It does not show that the programme is badly run. Everything we read about the rehabilitation work itself describes careful projects, including a partnership with an arboretum on a naturalisation project. A programme spending $500,000 a year well is spending $500,000 a year well.

What the arithmetic shows is that the funding formula and the size of the task were never connected to each other, and that no amount of good administration inside a half-cent dedication set in 1990 closes a backlog of that size. That is a design fact, not a performance one, and it is visible from division that anybody could have done at any point in the last thirty-six years.

What One Operator Contributes

Turn the fee around and look at it from a single licensed site, because the number surprised us.

Ours, at the historical half-cent dedication:

  • A site extracting 100,000 tonnes a year contributes $500 a year to the abandoned site fund
  • At 500,000 tonnes: $2,500
  • At 2,000,000 tonnes: $10,000

A substantial quarry moving two million tonnes a year contributes ten thousand dollars annually to the rehabilitation of legacy sites. On our earlier arithmetic, that is enough to fund somewhere between one-fifteenth and one-twenty-fifth of a single site rehabilitation, per year, from one of the largest operations in the province.

The point is not that operators should pay more. That is a policy question and we have no view we would defend in print. The point is that the contribution is small enough that no operator has any reason to think about it, and a levy nobody notices is a levy nobody argues about, in either direction.

Set that beside the municipal share on the same tonnage. At the historical breakdown, the same two-million-tonne site sends six cents a tonne to the local municipality, which is $120,000 a year, and half a cent to the abandoned pits fund, which is $10,000. A host municipality is receiving twelve times what legacy rehabilitation receives from the same truck.

That asymmetry is the reason the fee is politically stable and the reason the backlog is not closing. Both follow from the same distribution.

The Operator's Own Obligation Is Elsewhere

Everything above concerns legacy sites. A licensed operator's obligation to rehabilitate its own pit sits in a different place, and the separation has consequences worth drawing out.

An operating site has a site plan, progressive rehabilitation obligations as extraction advances, final rehabilitation when it ends, and an annual compliance assessment report that the operator completes and submits to the ministry, and to the local municipality where the site sits in one [3].

The trustee's stated responsibilities include the rehabilitation of sites where licences or permits have been revoked [2], which tells you what happens at the boundary: if a licence is revoked, the site can fall to the Trust.

We did not obtain the security provisions governing a licensed operator's own rehabilitation obligation, and that is a real gap in an article with rehabilitation security in its queue entry. What we can observe is the structure the sources describe.

Ours: the system has an obligor-based mechanism for active sites and a fund-based mechanism for sites with no obligor, and a route between them. Revocation moves a site from the first category to the second, which means it moves from a mechanism backed by a licensee's assets and its interest in continuing to trade, to a mechanism running on $400,000 to $600,000 a year shared with 7,900 others.

That transition is the one worth watching, and public interest material we read observes that licence surrender or revocation is infrequent even where pits have been inactive for long periods.

The Scarce Thing Is Not The Rock

One point about what an aggregate business actually owns, because it explains the incentives in the previous sections and it is frequently stated backwards.

Sand, gravel and stone are abundant. Ontario has enormous quantities of all three. What is scarce is not the material.

What is scarce is a permitted, zoned, approved extraction site within economic haulage distance of where the material is needed. Aggregate is heavy, low in value per tonne, and priced substantially by trucking. A deposit forty kilometres further from the market is a different commodity from the same deposit next to it.

So the asset is the approval, attached to a location. Not the reserve.

Ours, and three consequences follow.

The licence has an option value that the annual fee does not reflect. An existing approval on a zoned site near a market would in many cases be difficult, slow or impossible to replicate today. Holding it is holding something whose replacement cost is unrelated to its carrying cost.

Depletion and obligation move together, and only one is usually measured. Every tonne removed converts a scarce approved reserve into revenue and adds incrementally to the area requiring rehabilitation. A business tracking tonnes sold and not tracking hectares disturbed is measuring one side of the same transaction.

Final rehabilitation extinguishes the asset, not just the liability. This is the point that makes the deferral behaviour rational rather than merely lazy. Rehabilitating a worked-out pit does not simply discharge an obligation at a cost. It closes the option to reopen, extend, or use the approval for anything else, permanently.

Set that beside a minimum annual fee in the low hundreds of dollars and the shape of the problem is clear. The framework charges almost nothing to keep an option alive and requires a large irreversible payment to give it up, and it then relies on progressive rehabilitation obligations and a regulator's willingness to revoke to counteract an incentive it created.

We state no accounting position on any of this, having obtained no guidance on depletion, wasting assets or rehabilitation provisions [6]. What we would say is that a valuation of an aggregate business built on remaining reserves, without the obligation attached to extracting them, has valued the upside of a transaction and not the transaction.

The Sites That Are Neither

That observation deserves its own section, because it describes a category the whole framework handles badly.

The public interest paper we read records that delays to progressive and final rehabilitation seem frequent and common, and that licence surrender or revocation is infrequent even when pits have been inactive for long periods [4].

Put those together and there is a third state, between operating and abandoned. A site holds a licence, is not extracting, and is not rehabilitated.

Ours, on why that state is stable. Consider the incentives at an inactive licensed pit.

Holding the licence is cheap. The Class A annual fee is the greater of a per-tonne amount and a minimum, historically $200 for Class A and $100 for Class B under O. Reg. 244/97 [5]. A site extracting nothing pays the minimum.

Rehabilitating is expensive and irreversible. Final rehabilitation ends the option to extract again if markets or approvals change, and aggregate reserves near markets are scarce and valuable.

The licence is the option. An extraction approval on a zoned, permitted site is worth a great deal and would be difficult or impossible to obtain again.

So an inactive licence holder pays a small annual fee to preserve a valuable option and defer an expensive obligation. That is a rational position and the framework does not price it.

We are not alleging that operators are doing this deliberately. We are pointing out that if the minimum annual fee is in the low hundreds of dollars and final rehabilitation is in the tens or hundreds of thousands, the carrying cost of deferral is close to zero and the framework supplies no countervailing pressure other than a regulator's willingness to revoke, which the same source says is infrequent.

And The Uses That Make It Permanent

One further mechanism the same paper identifies, and it is a good observation that we have not seen made in financial terms.

The paper notes that rehabilitation is delayed by potential other uses of pits, such as recycling, which introduces industrial uses into extraction sites and alters interim uses into permanent ones [4].

Think about what an interim use does to the economics of rehabilitation.

An exhausted pit is a hole with a rehabilitation liability attached. It generates nothing and costs money to fix. Now put a recycling operation, a transfer station, a concrete plant or a storage yard in it. The hole becomes a revenue-generating industrial site whose value depends on its remaining a hole.

Ours. That transformation changes the rehabilitation decision from "when do we spend the money" to "when do we shut down a profitable operation and then spend the money." The second question has a much later answer than the first, and it gets later every year the interim use succeeds.

It also creates a valuation problem. A site carried at some value reflecting an interim industrial use, with a rehabilitation obligation attached that the interim use is deferring, has two facts about it that point in opposite directions and are usually recorded in different places by different people.

We did not obtain any accounting guidance and state no position on how either should be carried. What we would say is that an interim use is not a neutral efficiency. It is a change in the expected timing of a liability, and expected timing is most of what a long-dated liability is.

Tonnes Out, Hectares Disturbed

There is a mismatch at the centre of the funding design that we think explains a good deal.

The fee is charged per tonne removed. Rehabilitation cost is driven by disturbed area, depth, water table, slope stability and the end use required, not by tonnage.

Those diverge, and they diverge systematically.

A deep quarry on a small footprint removes an enormous tonnage from a comparatively small disturbed area. It pays a great deal of fee and creates a rehabilitation problem concentrated in hectares rather than spread across them.

A shallow sand and gravel pit over a wide area removes far less tonnage per hectare disturbed. It pays proportionately little fee and leaves proportionately more surface to restore.

Ours, and offered as a mechanism rather than a measurement, because we have no data on the distribution of Ontario sites by depth or footprint. If the fee is meant in any part to relate extraction to the cost of putting land back, tonnage is the wrong basis for it, because the relationship between tonnes removed and hectares disturbed varies by an order of magnitude across site types.

The same mismatch appears at the municipal end, where a host municipality's road wear and traffic burden does track tonnage closely, which is presumably why tonnage was chosen. So the basis is well matched to 76 percent of what the fee does and poorly matched to the three percent.

That is a coherent explanation for the design and it is not a defence of it. A levy calibrated to its majority purpose will be miscalibrated for its minority one, and the minority one here is the only part with an environmental obligation attached.

What The Operator Actually Files

Two reporting obligations run alongside the fee and they are worth knowing because they are where an operator's exposure is documented.

The annual production report. Under O. Reg. 244/97, every licensee and every holder of an aggregate permit files with the Aggregate Resources Trust, on or before 31 January, an annual production report setting out the quantity of aggregate removed from the site in each month of the previous year [5]. The annual fee follows, payable on or before 15 March.

The compliance assessment report. Ontario describes a report submitted to the ministry through the Natural Resources Information Portal or by mail, with a copy to the local municipality where the site is within one [3].

Ours, on why the first one matters more than it looks. A monthly production report filed annually with the trustee creates a permanent, granular, self-reported record of extraction by site by month, held by the body that also administers rehabilitation and publishes production statistics.

That record is the denominator for everything. It sets the fee, it sets the municipal distribution, and it is the evidence of how much material has come out of a given hole. An operator whose production reporting and whose internal tonnage records diverge has a problem that surfaces at exactly the wrong moment, because the trustee's copy is the one everyone else works from.

The minimum royalty for Crown aggregate is a separate matter and was set at 25 cents per tonne and subsequently 50 cents under O. Reg. 499/06 [5], which is several times the whole licence fee and applies only to Crown material.

The One Part That Is Indexed

One feature of the design does adjust over time and it is worth crediting.

The trustee states that fees and royalties are adjusted annually to account for inflation in accordance with Regulation 244/97, following the Ontario Consumer Price Index, and that the ministry posts the adjusted figures before 1 January each year [1].

So the half-cent of 1990 is not still half a cent in nominal terms. The real value of the dedication has been maintained.

That is genuinely better design than the alternative and it is worth saying so, because this article has been critical and the criticism should be precise.

What indexation preserves is purchasing power per tonne. What it does not do is any of the following, ours:

It does not track the backlog. If the number of sites needing rehabilitation is larger than assumed, or grows, indexation does nothing about it.

It does not track rehabilitation cost specifically. A general consumer price index and the cost of earthmoving, hydroseeding, slope stabilisation and long-term monitoring are different series, and construction cost has not tracked CPI over the last several years.

It does not track extraction volume. The dedication is per tonne, so total funding falls when extraction falls. The programme's own stated funding range is described as based on recent levels of extraction, which is a candid acknowledgement that the budget moves with the market rather than with the task.

So the funding is indexed to the wrong things, twice. Per unit it follows consumer prices rather than rehabilitation costs, and in aggregate it follows aggregate demand rather than the number of holes in the ground.

If You Operate A Pit Or Quarry

Five things, in the order we would look at them.

Do not treat your fee as pre-funding your own rehabilitation. It funds legacy sites you have no connection to. Your own obligation sits in your site plan and is yours to fund separately.

Reconcile your production reporting to your internal tonnage. The annual production report to the trustee, due 31 January, is the record everyone else works from. It sets your fee, the municipal distribution and the documented extraction history of your site.

Cost your progressive rehabilitation properly and do it as you go. Progressive rehabilitation is an obligation and it is also the only version of this cost that is cheap, because the equipment is already on site and the disturbed area is fresh.

If you hold an inactive licence, know what deferral is actually costing you. On the historical figures the minimum annual fee is in the low hundreds. The obligation you are deferring is not, and it does not get smaller.

If you have introduced an interim use into a worked-out area, be explicit that you have deferred a liability rather than resolved one. A revenue-generating hole is still a hole with an obligation attached, and the interim use makes the eventual decision harder rather than easier.

If You Advise One

Four checks we would run on any aggregate operator engagement.

Whether the rehabilitation obligation is recognised at all, and on what basis. Progressive and final rehabilitation are contractual and regulatory obligations attached to a wasting asset. We state no recognition position, but a set of accounts in which they appear nowhere is a set of accounts worth asking about.

Whether the site is carried on a basis that assumes an interim use continues. If a worked-out area now hosts recycling or storage, the value of that use and the obligation it is deferring are two facts about the same land, and they are usually held by different people.

The production report against the ledger. Tonnage reported to the trustee drives fees payable to three recipients. A reconciliation difference is a liability in at least one direction.

For an inactive licence, whether anyone has decided anything. Holding a licence on a non-producing site is a decision to defer, and it should be a decision rather than a default. The annual minimum fee is small enough that nothing prompts a review.

And one thing to resist. Do not describe the licence fee to a client as a rehabilitation levy. On the trustee's own published distribution, 76 percent goes to municipalities and three percent goes to rehabilitation and research combined. It is a municipal compensation payment with a rehabilitation rider.

What To Do

If you take one thing from this article, take the division. Roughly $400,000 to $600,000 a year, against a backlog put at some 7,900 sites, is $50 to $76 per site per year. No amount of good administration inside that number closes the backlog.

If you take two, take the distribution. Sixty-one percent to the local municipality, fifteen to the upper tier, three to rehabilitation and research together. The ratio of municipal to remediation is 25.3 to one, and the fee is best understood as a host compensation instrument rather than an environmental one.

If you are advising an aggregate operator this quarter, the highest-value single question is whether the client holds any licence on a site that is not producing and not rehabilitated. That is where an unpriced deferral sits, and the annual fee is too small to prompt anyone to look.

The Limits Of This Analysis

Long and specific, because a limits section that is short is decoration.

The 7,900 site figure carries two of our five headline claims and it is weak. It comes from testimony at 2012 hearings, reproduced in a public interest paper, and the speaker's own wording was approximately 7,900 sites or more. It is fourteen years old and it was an advocacy submission. If the real figure is half that, every horizon in this article halves and remains absurd. If it is double, they double.

The $400,000 to $600,000 is a quoted statement, not an audited figure. It comes from the programme's co-ordinator describing the programme's own budget. We did not obtain the Trust's financial statements.

The per-site rehabilitation cost is entirely invented. We could not source one, which is why we ran the horizon across a ten-fold band from $50,000 to $500,000 rather than picking a number.

The cents-per-tonne figures are historical. The 11.5 cent fee and its component split come from older material. Fees are indexed annually and we did not retrieve the current figure, so we used the trustee's published percentage distribution for anything load-bearing and treated the cents as illustration.

We did not obtain the Aggregate Resources Act. Everything statutory reaches us through regulation text, provincial policy documents or the trustee's own description.

We did not obtain the rehabilitation security provisions for licensed operators. That is a gap in an article whose queue entry named rehabilitation security, and it is why the operator's own obligation is described structurally rather than quantified [6].

The tonnes-versus-hectares argument is a mechanism with no data behind it. We have no distribution of Ontario sites by depth or footprint and we say so where we make the argument.

The inactive licence argument is inference about incentives. We rely on a public interest paper's observation that revocation is infrequent, and we have no data on how many licences sit inactive or for how long.

Two of our sources are public interest advocacy papers. They are cited for statements of fact that they attribute, including a quoted programme co-ordinator, and they are parties to a policy debate. We have tried to use them for attributed facts rather than for conclusions, and readers should weigh them accordingly.

We reached no accounting conclusion and state no recognition or measurement position on rehabilitation obligations, site carrying values or interim uses.

The option value argument is unquantified. We assert that an existing approval on a zoned site near a market would be difficult to replicate and therefore carries value unrelated to the annual fee. We did not obtain any data on approval timelines, refusal rates, or the market value of aggregate licences, and we have put no number on it anywhere.

We say nothing about how a licence should be valued or carried. The observation that a reserve-based valuation omits the obligation attached to extracting the reserve is a comment about what a valuation should contain, not a method for building one.

This is Ontario, and nothing here is advice on a particular site.

Frequently Asked Questions

How is Ontario's aggregate licence fee distributed?
On the trustee's own published notices, approximately 61 percent to the local municipality, 15 percent to the upper-tier municipality, and 3 percent to the Aggregate Resources Trust for rehabilitation and research, with the remainder to the Crown. Municipalities take 76 percent against three percent for rehabilitation and research combined.
Does my licence fee fund the rehabilitation of my own site?
No. The fee's rehabilitation component funds the Management of Abandoned Aggregate Properties programme, which addresses legacy sites that stopped operating before licensing was required. A licensed operator's own rehabilitation obligation sits in its site plan and is funded separately.
How much money does the abandoned site programme have?
The programme's co-ordinator is quoted as saying that based on recent levels of extraction, approximately $400,000 to $600,000 is made available annually. That is a quoted statement rather than an audited figure and we did not obtain the Trust's accounts.
How does that compare to the size of the backlog?
Against a figure of approximately 7,900 abandoned sites given in 2012 testimony, it is $50.63 to $75.95 per site per year. At an assumed $150,000 per site rehabilitation cost the backlog clears in 1,975 to 2,962 years, assuming no new abandonments and no cost inflation. The site count is the weakest number in our analysis.
Where did the half-cent dedication come from?
On the account given by the programme's co-ordinator, when the Act came into effect in 1990 the aggregate industry, through the association now known as the Ontario Stone, Sand and Gravel Association, decided to dedicate half a cent per tonne of licence fees to rehabilitating legacy sites. It was an industry agreement, expressed in cents rather than as a proportion of the task.
Are the fees adjusted over time?
Yes. The trustee states that fees and royalties are adjusted annually for inflation under Regulation 244/97 following the Ontario Consumer Price Index, with adjusted figures posted before 1 January. That preserves purchasing power per tonne. It does not track the backlog, rehabilitation cost specifically, or extraction volume.
What does an operator have to file?
Under O. Reg. 244/97, every licensee and aggregate permit holder files an annual production report with the Trust by 31 January setting out monthly quantities removed in the previous year, with the annual fee due by 15 March. Ontario separately describes a compliance assessment report to the ministry, copied to the local municipality where applicable.

References

  1. The Ontario Aggregate Resources Corporation, published aggregate fee notices for 2023-24, 2024-25 and 2025-26. Source of the distribution of fees collected from licences, wayside permits and aggregate permits, being approximately 3 percent to the Aggregate Resources Trust for rehabilitation and research, 61 percent to the local municipality in which the site is located and 15 percent to the upper-tier municipality; and of the statement that fees and royalties are adjusted annually for inflation in accordance with Regulation 244/97 following the Ontario Consumer Price Index, with adjusted figures posted before 1 January each year. Note: the trustee's own published notices, stating the same distribution across three consecutive years. The strongest source here and the basis for everything load-bearing. TOARC
  2. Provincial policy material and trustee description of the Aggregate Resources Trust, used for the historical 11.5 cent per tonne licence fee and its component breakdown of 3.5 cents to the Crown, 6 cents to the local municipality, 1.5 cents to the county or regional municipality and 0.5 cent to the abandoned pit and quarry fund; for the incorporation of the Ontario Aggregate Resources Corporation in 1997 as trustee under section 6.1 of the Act; and for the trustee's stated responsibilities including collecting and disbursing aggregate fees, rehabilitating abandoned pits and quarries, rehabilitating sites where licences or permits have been revoked, publishing production statistics and providing education and training. Note: the cents figures are historical and superseded by annual indexation. We use them as illustration and rely on the percentage distribution in ref1 for anything that matters.
  3. Government of Ontario, aggregate resources pages. Source of the description of legacy sites as pits and quarries on private land that stopped operating before they were required to obtain a licence, and of the statement that where the landowner has granted permission these can be rehabilitated by the Ontario Aggregate Resources Corporation under the Management of Abandoned Aggregate Properties programme; and of the compliance assessment report obligation, submitted online through the Natural Resources Information Portal or by mail, with a copy to the local municipality where the site is within one. Note: the province describing its own programme. Ontario
  4. Two public interest papers on the rehabilitation of pits and quarries under the Aggregate Resources Act. Used for the programme co-ordinator's quoted statement that the industry dedicated half a cent per tonne in 1990 and that based on recent extraction levels approximately $400,000 to $600,000 is made available annually; for the figure of approximately 7,900 abandoned sites or more, given in 2012 hearings testimony; and for the observations that delays to progressive and final rehabilitation seem frequent and common, that licence surrender or revocation is infrequent even where pits have been inactive for long periods, and that rehabilitation is delayed by interim uses such as recycling which alter interim uses into permanent ones. Note: advocacy papers, and parties to a policy debate. We have used them for attributed statements of fact rather than for conclusions. The 7,900 figure carries two of our headline claims and is the weakest number in the article.
  5. A reproduction of O. Reg. 244/97 under the Aggregate Resources Act. Used for the requirement that every licensee and every holder of an aggregate permit file an annual production report with the Aggregate Resources Trust on or before 31 January setting out monthly quantities removed in the previous year; for the annual fee payable on or before 15 March, being the greater of a per-tonne amount and a minimum stated historically as $200 for a Class A licence and $100 for a Class B; for the allocation of one twenty-third to the Aggregate Resources Trust for rehabilitation and research under section 6.1(2) of the Act; and for the minimum royalty of 25 cents per tonne, substituted at 50 cents by O. Reg. 499/06. Note: a reproduction of regulation text on a third-party document site, not an official consolidation, and carrying amendments whose currency we could not verify. The per-tonne and minimum figures are historical.
  6. The Aggregate Resources Act itself, and the rehabilitation security provisions applying to licensed operators, were NOT obtained for this article. Note: recorded as a reference deliberately so the absence sits on the list rather than buried in the limits. The queue entry for this topic named rehabilitation security, and we have described the operator's own obligation structurally rather than quantifying it, because we did not read the provisions that govern it. No accounting guidance was consulted either, and we state no recognition or measurement position anywhere in this article.